Bldg.39 - rm. 328 Building Power Shutdown - (120V/208V)
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Fri May 17 11:04:14 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <sgilliga@plant.mit.edu>
Date: Fri, 17 May 2013 11:03:20 -0400
Message-ID: <31501F5672BF43D593BFE2103E829B05@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Building Power Shutdown is for Bldg. 39 - rm 328 - PL3 is on Wednesday, May 22, 2013 from 5:00am - 7:00am is for your information and approval. Any questions please contact Steve Gilligan x3-8079.
Would you please let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: May 22, 2013
Day: Wednesday
Time: 5:00am -7:00am
Building(s): 39
Room(s): 328
System: building power 120V/208V
Duration: 5:00am - 7:00am
Reason:
This is to install a new circuit.
Effect:
Loss of building power to area for duration of this shutdown.