Bldg. NW14- 1323 - Building Power Shutdown - Argon Laser, Kripton Laser, Optical table, Innova300
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Fri May 17 09:44:54 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <sgilliga@plant.mit.edu>
Date: Fri, 17 May 2013 09:44:47 -0400
Message-ID: <9C1C2C746B3E47EC9381D975CA0A013E@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Building Power Shutdown - Airgon Laser, Kripton Laser, Optical table, Innova300 is for bldg. NW14 - rm 1323 on Tuesday, May 21, 2013 from 5:00am - 7:00am is for your information and approval. Any questions please contact Steve Gilligan x3-8079.
Would you please let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: May 21, 2013
Day: Tuesday
Time: 5:00am - 7:00am
Building(s): NW14
Room(s): 1323 - near water drain
System: building power
Duration: 5:00am - 7:00am
Reason:
This is to have a circuit installation to PP1 - 120/208V panel shutdown.
Effect:
Loss of building power (Argon Laser, Kripton Laser, Optical table, Innova300) for the duration of this shutdown.