[169273] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 9-All Fire Alarm Shutdown (w/brief *live audible 1st/3rd party testing Tues/Wed 5/21, 22 at 6AM)

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue May 14 10:34:22 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <pjmurphy@MIT.EDU>
Date: Tue, 14 May 2013 10:34:14 -0400
Message-ID: <6163FBD9544C4472ABA80122F85F9441@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Fire Alarm Shutdown (w/brief *live audible 1st/3rd party testing Tues/Wed 5/21, 22 at 6AM) is for bldg. 9-All starting on Monday, May 20, 2013 from 6:00am til 11:00am and then on Tuesday and Wednesday, May 21st and 22nd it will be 6:00am til 7:00am, is for your information and approval.  Any questions please contact Billy Homeyer x8--0432.


Would you please let us know if this does or does not have your approval.

Thank you,

Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: May 20, 2013
Day: Monday
Time: Mon - 6:00am - 11:00am,, Tues/Wed 6:00am - 7:00am
Building(s): 9
Room(s): All
System: Fire alarms
Duration: Mon - 6:00am - 11:00am,, Tues/Wed 6:00am - 7:00am
Reason: 
We request bldg 9-all fire alarm shutdowns on Monday, Tuesday and Wednesday, May 20th, 21st and 22nd, 2013 - finals week - as follows;

from 6 AM to 11 AM on Monday 5/20 for MacNichol Electric (Tom Durant 978-930-6001) and Simplex (Rich Perron 781-603-7799) to tie-in and program elevator related fire alarm devices (alt & primary recall, firefighters hat, damper, fan); 

and from 6 AM to 7 AM on Tuesday and Wednesday, 5/21,22 to conduct *live audible 1st and then 3rd party testing of the bldg 9 fire alarm system in order to test the new devices. 3rd party testing on Wednesday 5/22 will be witnessed by JMBCo (Wayne Maginnis 617-212-2059) 

and as part of the bldg 9 elevator modernization project by Commodore Builders (Ralph D'Antonio 617-719-
4682), Paul Murphy 4-6163 is the MIT project manager.



Effect: 
Loss of fire alarms for the duration of this shutdown. 

home help back first fref pref prev next nref lref last post