[169157] in Hotline Meeting
Approved - Bldg. 7-304/206 Low Pressure Steam Shutdown
daemon@ATHENA.MIT.EDU (Jennifer Garland)
Fri May 10 14:13:15 2013
From: Jennifer Garland <jennygar@plant.mit.edu>
To: Jim Harrington <lordjim@MIT.EDU>, "laugh@mit.edu" <laugh@MIT.EDU>,
"tommyl@mit.edu" <tommyl@MIT.EDU>, "myersm@MIT.EDU" <myersm@MIT.EDU>,
"skendall@mit.edu" <skendall@MIT.EDU>,
OPS RM Campus Services Main
<rm-mcs@MIT.EDU>,
Ops Custodial Admin & Support Staff <cust-staff@MIT.EDU>,
"gearin@mit.edu" <gearin@MIT.EDU>,
"segaloff@MIT.EDU" <segaloff@MIT.EDU>, "jcoen@mit.edu" <jcoen@MIT.EDU>,
"gayle@mit.edu" <gayle@MIT.EDU>, "Michael
Smith" <masmith@MIT.EDU>,
"sbghosh@MIT.EDU" <sbghosh@MIT.EDU>, "fenner@mit.edu" <fenner@MIT.EDU>,
"annm@mit.edu" <annm@MIT.EDU>, "mberg@mit.edu" <mberg@MIT.EDU>,
"jbnorman@mit.edu" <jbnorman@MIT.EDU>,
"bridburg@MIT.EDU" <bridburg@MIT.EDU>, "whc@mit.edu" <whc@MIT.EDU>,
"hillery@mit.edu" <hillery@MIT.EDU>,
"kyegian@MIT.EDU" <kyegian@MIT.EDU>,
"shutdowns@mit.edu" <shutdowns@MIT.EDU>,
"whomeyer@mit.edu"
<whomeyer@MIT.EDU>,
"ksemerj@mit.edu" <ksemerj@MIT.EDU>,
Gary Saffie
<gsaffie@plant.mit.edu>,
Ops RM Shutdown <rm-shutdown@MIT.EDU>, DOF EHS
<dof-ehs@MIT.EDU>,
"cp-command@mit.edu" <cp-command@MIT.EDU>,
"safety@mit.edu" <safety@MIT.EDU>, Operators <Operators@plant.mit.edu>,
"DOF
Customer Service Center" <dof-csc@MIT.EDU>,
"Ops Custodial Admin & Support
Staff" <cust-staff@MIT.EDU>
CC: "jennygar@mit.edu" <jennygar@MIT.EDU>, "biss@mit.edu" <biss@MIT.EDU>
Date: Fri, 10 May 2013 14:13:07 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AD41F01A@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following Approved Low Pressure Steam Shutdown is for Bldg. 7-304/206 is on Saturday, May 11, 2013 from 6:00am - 2:00pm is for your information. Any questions please contact Billy Homeyer x8-0432.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: May 11, 2013
Day: Saturday
Time: 6:00am - 2:00pm
Building(s): 7
Room(s): building
System: Low Pressure Steam
Duration: 6:00am - 2:00pm
Reason:
We request a bldg 7-304/206 low pressure steam shutdown at 6 AM to 2 PM on Saturday, May 11th, 2013 to demo existing steam pipe and install new valves and prep to refeed units on 3rd floor as part of the SAP renovation/former Rotch Library project by Renovations, Inc. (Jim Abbisso 617-594-7650). Biss Teelucksingh 2-5972 is the MIT project manager on behalf of Billy Homeyer.
Effect:
Loss of low pressure steam to building for the duration of this shutdown.