Approved - Bldg. 7-304/206 Low Pressure Steam Shutdown

daemon@ATHENA.MIT.EDU (Jennifer Garland)
Fri May 10 14:13:15 2013

From: Jennifer Garland <jennygar@plant.mit.edu>
To: Jim Harrington <lordjim@MIT.EDU>, "laugh@mit.edu" <laugh@MIT.EDU>,
        "tommyl@mit.edu" <tommyl@MIT.EDU>, "myersm@MIT.EDU" <myersm@MIT.EDU>,
        "skendall@mit.edu" <skendall@MIT.EDU>,
        OPS RM Campus Services Main
	<rm-mcs@MIT.EDU>,
        Ops Custodial Admin & Support Staff <cust-staff@MIT.EDU>,
        "gearin@mit.edu" <gearin@MIT.EDU>,
        "segaloff@MIT.EDU" <segaloff@MIT.EDU>, "jcoen@mit.edu" <jcoen@MIT.EDU>,
        "gayle@mit.edu" <gayle@MIT.EDU>, "Michael
 Smith" <masmith@MIT.EDU>,
        "sbghosh@MIT.EDU" <sbghosh@MIT.EDU>, "fenner@mit.edu" <fenner@MIT.EDU>,
        "annm@mit.edu" <annm@MIT.EDU>, "mberg@mit.edu" <mberg@MIT.EDU>,
        "jbnorman@mit.edu" <jbnorman@MIT.EDU>,
        "bridburg@MIT.EDU" <bridburg@MIT.EDU>, "whc@mit.edu" <whc@MIT.EDU>,
        "hillery@mit.edu" <hillery@MIT.EDU>,
        "kyegian@MIT.EDU" <kyegian@MIT.EDU>,
        "shutdowns@mit.edu" <shutdowns@MIT.EDU>,
        "whomeyer@mit.edu"
	<whomeyer@MIT.EDU>,
        "ksemerj@mit.edu" <ksemerj@MIT.EDU>,
        Gary Saffie
	<gsaffie@plant.mit.edu>,
        Ops RM Shutdown <rm-shutdown@MIT.EDU>, DOF EHS
	<dof-ehs@MIT.EDU>,
        "cp-command@mit.edu" <cp-command@MIT.EDU>,
        "safety@mit.edu" <safety@MIT.EDU>, Operators <Operators@plant.mit.edu>,
        "DOF
 Customer Service Center" <dof-csc@MIT.EDU>,
        "Ops Custodial Admin & Support
 Staff" <cust-staff@MIT.EDU>
CC: "jennygar@mit.edu" <jennygar@MIT.EDU>, "biss@mit.edu" <biss@MIT.EDU>
Date: Fri, 10 May 2013 14:13:07 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AD41F01A@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following Approved Low Pressure Steam Shutdown is for Bldg. 7-304/206 is on Saturday, May 11, 2013 from 6:00am - 2:00pm is for your information.  Any questions please contact Billy Homeyer x8-0432.


Thank you,


Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: May 11, 2013
Day: Saturday
Time: 6:00am - 2:00pm
Building(s): 7
Room(s): building
System: Low Pressure Steam
Duration: 6:00am - 2:00pm
Reason: 
We request a bldg 7-304/206 low pressure steam shutdown at 6 AM to 2 PM on Saturday, May 11th, 2013 to demo existing steam pipe and install new valves and prep to refeed units on 3rd floor as part of the SAP renovation/former Rotch Library project by Renovations, Inc. (Jim Abbisso 617-594-7650).  Biss Teelucksingh 2-5972 is the MIT project manager on behalf of Billy Homeyer.



Effect: 
Loss of low pressure steam to building for the duration of this shutdown.