[169148] in Hotline Meeting
Bldg. 7-304/206 Low Pressure Steam Shutdown
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Fri May 10 11:35:32 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <biss@MIT.EDU>
Date: Fri, 10 May 2013 11:35:25 -0400
Message-ID: <B44BA0972C5B47D79A99FEDB179B24D2@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Low Pressure Steam Shutdown is for Bldg. 7-304/206 is on Saturday, May 11, 2013 from 6:00am - 2:00pm is for your information and approval. Any questions please contact Billy Homeyer x8-0432.
Would you please let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: May 11, 2013
Day: Saturday
Time: 6:00am - 2:00pm
Building(s): 7
Room(s): building
System: Low Pressure Steam
Duration: 6:00am - 2:00pm
Reason:
We request a bldg 7-304/206 low pressure steam shutdown at 6 AM to 2 PM on Saturday, May 11th, 2013 to demo existing steam pipe and install new valves and prep to refeed units on 3rd floor as part of the SAP renovation/former Rotch Library project by Renovations, Inc. (Jim Abbisso 617-594-7650). Biss Teelucksingh 2-5972 is the MIT project manager on behalf of Billy Homeyer.
Effect:
Loss of low pressure steam to building for the duration of this shutdown.