Approved Bldg. 7 - 3rd Floor Sprinkler System Shutdown Notification

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Wed May 8 15:46:10 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <biss@MIT.EDU>
Date: Wed, 8 May 2013 15:45:51 -0400
Message-ID: <5872A4698BB44918A5A24B8657374FCD@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following sprinkler system, shutdown notification for Bldg. 7 - 3rd Floor on Thursday, May 9, 2013 from 6am to 9am is for your information. No response is required to this notification. Any questions, please contact Billy Homeyer  @ 8-0432

We appreciate your patience while the repairs/renovations are in progress.

Thank you
Bill Lombard
Operations Center


Type: Normal
Date: May 9, 2013
Day: Thursday
Time: 6am
Building(s): 7
Room(s): 3rd Floor
System: Fire Protection Water
Duration: 3 hours
Reason: 
To demo existing sprinkler system in 7-304 (temp heat detectors are in place & tested)

Effect: 
Loss of fire protection water. The Safety Office will be advised of this, and notify the Fire Department.