Bldg. 26- Normal Power & Lighting Shutdown

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue May 7 08:02:12 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <rlucas@MIT.EDU>
Date: Tue, 7 May 2013 08:01:39 -0400
Message-ID: <BF79CAD755C64C6EA873D8639DB4CDAA@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Normal Power & Lighting Shutdown is for bldg. 26 - All on Wednesday, May 29, 2013 from 8:00am - 9:00am is for your information and approval.  Any questions please contact Rich Lucas 617-324-6801.


Would you please let us know if this does or does not have your approval.


Thank you,


Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: May 29, 2013
Day: Wednesday
Time: 8:00am - 9:00am
Building(s): 26
Room(s): bldg.
System: access controls,building power,elevator, computers, telephones,lighting, corridors/stairs, chilled water, condenser water, supply ventilation,cooling, exhaust lab/general/toilet, exhaust hood
Duration: 8:00am - 9:00am
Reason: 
This is to replace circuit breakers for this area. Each circuit will only be off for 10 minutes at a time.

Effect: 
Loss of access controls,building power,elevator, computers, telephones,lighting, corridors/stairs, chilled water, condenser water, supply ventilation,cooling, exhaust lab/general/toilet, exhaust hoods for the duration of this shutdown. 