Approved - Bldg. 26-All Normal Emergency Power (Life-safety

daemon@ATHENA.MIT.EDU (Jennifer Garland)
Tue May 7 07:15:03 2013

From: Jennifer Garland <jennygar@plant.mit.edu>
To: "graham@mit.edu" <graham@mit.edu>, "abm@mit.edu" <abm@mit.edu>,
        "dudley@mit.edu" <dudley@mit.edu>, "nsteele@mit.edu" <nsteele@mit.edu>,
        "ljtrudel@mit.edu" <ljtrudel@mit.edu>,
        OPS RM Campus Services Main
	<rm-mcs@mit.edu>,
        Ops Custodial Admin & Support Staff <cust-staff@mit.edu>,
        "lsc-chairman@mit.edu" <lsc-chairman@mit.edu>,
        "lsc@mit.edu" <lsc@mit.edu>, "khewitt@mit.edu" <khewitt@mit.edu>,
        "elsye@MIT.EDU" <elsye@mit.edu>,
        "MIT
 Schedules Office" <schedules@mit.edu>,
        "wgibbs@rle.mit.edu"
	<wgibbs@rle.mit.edu>,
        "amcgurl@RLE.MIT.EDU" <amcgurl@rle.mit.edu>,
        "heatherg@mit.edu" <heatherg@mit.edu>,
        "shutdowns@mit.edu"
	<shutdowns@mit.edu>,
        "whomeyer@mit.edu" <whomeyer@mit.edu>,
        "ksemerj@mit.edu"
	<ksemerj@mit.edu>,
        Steven Gilligan <sgilliga@plant.mit.edu>,
        Gary Saffie
	<gsaffie@plant.mit.edu>,
        Ops RM Shutdown <rm-shutdown@mit.edu>, DOF EHS
	<dof-ehs@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        "DOF
 Customer Service Center" <dof-csc@mit.edu>,
        "Ops Custodial Admin & Support
 Staff" <cust-staff@mit.edu>
CC: "jennygar@mit.edu" <jennygar@mit.edu>, "jcombs@mit.edu" <jcombs@mit.edu>
Date: Tue, 7 May 2013 07:14:40 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13AD0B5B3C@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following Approved Normal Emergency Power Shutdown is for bldg. 26-All on Thursday, May 9, 2013 at 9:00PM til Friday, May 10, 2013 at 6:00am is for your information.  Any questions please contact Billy Homeyer x8-0432.



Thank you,


Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: May 9, 2013
Day: Thursday
Time: (Thu) 9:00PM - (Fri) 6:00AM
Building(s): 26
Room(s): All
System: Emergency Power, lighting, corr/stairs,hot/cold domestic water,supply ventilation,cooling, heating, exhaust -general, toilet, compressed control lab air, lab vacuum, condensate return, drainage -lab waste,sanitary, storm drain, fire alarm.
Duration: (Thu) 9:00PM - (Fri) 6:00AM
Reason: 
We request a bldg 26-all normal emergency power shutdown, from 9 PM on Thursday evening, May 9th to 6 AM on Friday morning, May 10th, 2013 for Annese Electric to install and tie-in a 225A circuit breaker in the emergency power switchgear for service to a new life-safety electrical closet being installed on the first floor as part of the bldg 26-life-safety systems upgrade project by Annese Electric (Joe Protano 781-726-2877). Paul Murphy 4-3163 and Jennifer Combs 3-7671 are the MIT project managers.

The following will be affected;

Emergency egress and stairwell lighting, exit signs - all floors All condensate and vacuum pumps All sump pumps and ejectors Control and lab air compressors Simplex fire alarm goes to battery back-up Autocall/TFX fire alarm goes to battery back-up DGP goes to battery back-up MRI lab oxygen depletion and Notifier panel (notifier to battery back-up)
AH20 and disregard alarms on any general exhaust fans Domestic water booster pumps and the control cabinet Toilet exhaust is assumed to be affected

Please note tel/data and security are on normal power and will not be affected.
The elevator is on normal power now, fed out of substation 1 The lecture hall 26-100 and a/v booth are also now on all normal power-USS1


Effect: 
Loss of Normal Emergency Power for the duration of this shutdown.



home help back first fref pref prev next nref lref last post