[168931] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Emergency Shutdown - Steam Humidification to Bldg. 68 - sub-basement

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue May 7 06:14:46 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <plyons@MIT.EDU>
Date: Tue, 7 May 2013 06:14:38 -0400
Message-ID: <4006D55AF920447FBAB5D23E9ACD604D@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Emergency Steam Humidification Shutdown is for Bldg. 68 sub-basement, Tuesday, May 7, 2013 from 7:00am - 11:00am is for your information. 

Any questions please contact Paul Lyons x3-5721.

We apologize for any inconvenience this may cause.

Thank you,

Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Emergency
Date: May 7, 2013
Day: Tuesday
Time: 7:00am - 11:00am
Building(s): 68
Room(s): sub-basement
System: low pressure steam, humidification
Duration: 7:00am - 11:00am - 4 hrs
Reason: 
This is to make emergency repairs to the steam valves on system. 

Effect: 
Loss of low pressure steam and humidification for the duration of this shutdown. 