Emergency Shutdown Bldg. 5 - Air Handler #1 - Supply Heating

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon May 6 09:30:58 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <mmcorrei@MIT.EDU>
Date: Mon, 6 May 2013 09:30:52 -0400
Message-ID: <6BCC7C9F0A6148F3B01DB458C917283C@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Emergency Shutdown of Air Handler #1 for Bldg. 5 is on Monday, May 6, 2013 from 9:30am til Finish is for your information.

Any questions please contact Mike Correira x8-9174.

We apologize for any inconvenience this may cause.


Thank you,


Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Emergency
Date: May 6, 2013
Day: Monday
Time: 9:30am til Finish
Building(s): 5
Room(s): bldg.
System: supply heating
Duration: 9:30am til Finish
Reason: 
Emergency repairs to be made to air handler #1. 

Effect: 
Loss of supply heating for the duration of this shutdown. 