CANCELLED - Bldg. 7-019 and surrounding area - Building Power

daemon@ATHENA.MIT.EDU (Jennifer Garland)
Thu May 2 13:39:02 2013

From: Jennifer Garland <jennygar@plant.mit.edu>
To: Ops Custodial Admin & Support Staff <cust-staff@MIT.EDU>,
        "segaloff@MIT.EDU" <segaloff@MIT.EDU>, "annm@mit.edu" <annm@MIT.EDU>,
        "shutdowns@mit.edu" <shutdowns@MIT.EDU>,
        DOF Customer Service Center
	<dof-csc@MIT.EDU>,
        Jim Harrington <lordjim@MIT.EDU>, "laugh@mit.edu"
	<laugh@MIT.EDU>,
        "tommyl@mit.edu" <tommyl@MIT.EDU>, "myersm@MIT.EDU"
	<myersm@MIT.EDU>,
        "skendall@mit.edu" <skendall@MIT.EDU>,
        "OPS RM Campus
 Services Main" <rm-mcs@MIT.EDU>,
        "gearin@mit.edu" <gearin@MIT.EDU>, "jcoen@mit.edu" <jcoen@MIT.EDU>,
        "gayle@mit.edu" <gayle@MIT.EDU>, "Michael
 Smith" <masmith@MIT.EDU>,
        "sbghosh@MIT.EDU" <sbghosh@MIT.EDU>, "fenner@mit.edu" <fenner@MIT.EDU>,
        "mberg@mit.edu" <mberg@MIT.EDU>, "jbnorman@mit.edu" <jbnorman@MIT.EDU>,
        "bridburg@MIT.EDU" <bridburg@MIT.EDU>, "whc@mit.edu" <whc@MIT.EDU>,
        "hillery@mit.edu" <hillery@MIT.EDU>,
        "kyegian@MIT.EDU" <kyegian@MIT.EDU>,
        Gary Saffie <gsaffie@plant.mit.edu>,
        "mobrien@mit.edu" <mobrien@MIT.EDU>
CC: "jennygar@mit.edu" <jennygar@MIT.EDU>,
        "sgilliga@mit.edu"
	<sgilliga@MIT.EDU>,
        David Shawles <dshawles@plant.mit.edu>,
        Mary Harrington
	<maryh@plant.mit.edu>,
        Scott McNey <smcney@plant.mit.edu>,
        "Kathleen M
 Mitchell (kmitch@mit.edu)" <kmitch@MIT.EDU>
Date: Thu, 2 May 2013 13:38:52 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF13ACBBE93F@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following CANCELLED Building Power Shutdown is for bldg. 7-019 and surrounding area on Friday, May 3, 2013 from 5:00am - 7:00am is for your information.  Any questions please contact Steve Gilligan x3-8079.


Thank you,


Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: May 3, 2013/// **CANCELLED**
Day: Friday
Time: 5:00am  - 7:00am////**CANCELLED**
Building(s): 7
Room(s): 019 and surrounding area
System: electrical power, access controls, computers
Duration: 5:00am - 7:00am 2 hrs
Reason: 
This is to wire  new circuits in this area.

Effect: 
Loss of electrical power for the duration of this shutdown.    **CANCELLED**