Bldg. E19-582 - Electrical Shutdown

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue Apr 30 14:06:31 2013

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <sgilliga@plant.mit.edu>
Date: Tue, 30 Apr 2013 14:06:21 -0400
Message-ID: <0487B1DDB749456D9FBFE66DBC1762E8@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Electrical Shutdown is for bldg. E19-582 on Friday, May 3, 2013 from 5:00am - 7:00am is for your information and approval.  Any questions please contact Steve Gilligan x3-8079.


Would you please let us know if this does or does not have your approval.


Thank you,


Jennifer M. Garland
Repair and Maintenance
4-4350

Type: Normal
Date: May 3, 2013
Day: Friday
Time: 5:00am - 7:00am
Building(s): E19
Room(s): 582
System: building power
Duration: 5:00am - 7:00am 
Reason: 
This is to tie in a 220V electrical recepticle in this room 582 (various outlet in room).

Effect: 
Loss of power to this room E19-582 for the duration of this shutdown. 