[168701] in Hotline Meeting
Bldg. 18-509,566, 566A - Electrical Power Shutdown
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue Apr 30 11:02:58 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <sgilliga@MIT.EDU>
Date: Tue, 30 Apr 2013 11:02:54 -0400
Message-ID: <6FA479EA931C4E16A0462B4671F41934@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Electrical Power Shutdown is for bldg. 18 - rm. 509,566, 566A is on Tuesday, May 7, 2013 from 4:00am - 7:00am is for your information and approval. Any questions please contact Steve Gilligan x3-8079.
Would you please let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: May 7, 2013
Day: Tuesday
Time: 4:00am - 7:00am
Building(s): 18
Room(s): 509,566, 566A
System: electrical power/exhaust laboratory
Duration: 4:00am - 7:00am - 3 hrs
Reason:
This is to install new circuits to electrical panel.
Effect:
Loss of electrical power for the duration of this shutdown.