Re: Bldg. NW14-All, Fan Supply and Fan Exhaust Hood Shutdown Request
daemon@ATHENA.MIT.EDU (Anthony Zolnik)
Mon Apr 29 16:33:13 2013
Message-ID: <517ED903.4020701@mit.edu>
Date: Mon, 29 Apr 2013 16:33:07 -0400
From: Anthony Zolnik <alz@MIT.EDU>
MIME-Version: 1.0
To: shutdown-response@MIT.EDU
CC: bdrink@MIT.EDU, mcweeney@MIT.EDU, wscott@plant.mit.edu, shutdowns@MIT.EDU
In-Reply-To: <47606C36EF7643F7A9D4EC2A3DEC937A@facilities.ms.mit.edu>
Content-Type: text/plain; charset=ISO-8859-1; format=flowed
Content-Transfer-Encoding: 7bit
Hi All,
We are all set with this portion of the shutdown:
> EF-1 730771 5/3/2013 7:30AM 2:30PM ROOM; 2324A, HOODS 2A,2B, 2C
> AH7-SF7 730770 5/3/2013 7:30AM 2:30PM ROOM; 2324A, HOODS 2A,2B, 2C
The other items do not affect AeroAstro so I cannot speak to them.
A
On 4/26/13 10:28 AM, shutdown-response@MIT.EDU wrote:
> The following Misc. Hood Exhaust Fans & Fan Supply #730770 AH47 SF7 shutdown request for Bldg. NW14-All on Friday, May 3, 2013 is for your information and response. Please see schedule below. Any questions please contact Joe McWeeney x3-8731.
>
> Would you please let us know whether this does or does not have your approval.
>
> Thank you,
> Bernadette Drinkwater
> Repair and Maintenance
> x3-0938
>
> NW14 - HOOD EXHAUST FAN SCHEDULE
> FCS TAG# DATE START TIME END TIME AREAS AFFECTED
> 709668 5/3/2013 7:30AM 2:30PM ROOMS; 5120
> 709669 5/3/2013 7:30AM 2:30PM ROOMS; 5120
> 704851 5/3/2013 7:30AM 2:30PM ROOMS; 5120
> 704311 5/3/2013 7:30AM 2:30PM ROOMS; 2112, 3112, 5112
> 704316 5/3/2013 7:30AM 2:30PM ROOM 5118 HOOD 2
> 704317 5/3/2013 7:30AM 2:30PM ROOM 5118 HOOD 1
> 730073 5/3/2013 7:30AM 2:30PM ROOM 2302A, 2 HOODS
> EF-1 730771 5/3/2013 7:30AM 2:30PM ROOM; 2324A, HOODS 2A,2B, 2C
> AH7-SF7 730770 5/3/2013 7:30AM 2:30PM ROOM; 2324A, HOODS 2A,2B, 2C
>
> NOTE: AS EACH FAN IS SERVICED (1-2 HOURS EACH); IT WILL BE PUT BACK INTO OPERATION
>
>
> Type: Normal
> Date: May 3, 2013
> Day: Friday
> Time: 7:00am - 3:00pm
> Building(s): NW14
> Room(s): See Schedule
> System: See Schedule
> Duration: 8 hours
> Reason:
> Annual Inspection and Maintenance of Fans cooling coil cleaning AH7 SF7
>
> Effect:
> Loss of exhaust and ventilation.
> AS EACH FAN IS SERVICED (1-2 HOURS EACH); IT WILL BE PUT BACK INTO OPERATION
>
> This message was sent the following recipients: wardle@mit.edu; alz@MIT.EDU; galanek@mit.edu; bobk@mit.edu; nmorriso@MIT.EDU; domara@mit.edu; jstark@plant.mit.edu; rm-wcs@mit.edu; jhaggert@mit.edu; jcrm@MIT.EDU; pbrenton@MIT.EDU; censabel@MIT.EDU; mfulton@mit.edu; hrycaj@psfc.mit.edu;
>