[168665] in Hotline Meeting
* Extended Bldg. E23 - 1st Floor Smoke Detector Shutdown
daemon@ATHENA.MIT.EDU (Nicole McKenna)
Mon Apr 29 10:08:09 2013
From: Nicole McKenna <nmckenna@plant.mit.edu>
To: OPS RM Campus Services East <rm-ecs@mit.edu>,
"Ops Custodial Admin &
Support Staff" <cust-staff@mit.edu>,
"bengel@mit.edu" <bengel@mit.edu>, "tquinn@mit.edu" <tquinn@mit.edu>,
"brig@med.mit.edu" <brig@med.mit.edu>,
"fris@med.mit.edu" <fris@med.mit.edu>,
"sher@med.mit.edu" <sher@med.mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"k_brown@MIT.EDU" <k_brown@mit.edu>,
"monaglek@MIT.EDU" <monaglek@mit.edu>,
"shutdowns@mit.edu"
<shutdowns@mit.edu>,
"whomeyer@mit.edu" <whomeyer@mit.edu>,
Ops RM Shutdown
<rm-shutdown@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
"DOF
Customer Service Center" <dof-csc@mit.edu>,
Ops RM Fire Protection Team
<rm-fire-prot-team@mit.edu>
CC: "biss@mit.edu" <biss@mit.edu>
Date: Mon, 29 Apr 2013 10:07:57 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF1244B3C6EE@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following smoke detector shutdown for building E23-1st floor has been extended to include Monday evening, April 29, 2013 and Tuesday evening, April 30, 2013 from 6 PM to 4 AM each day. No response is required to this notification. Any question please contact Billy Homeyer ext. 8-0432.
We appreciate your patience while the repairs/renovations are in progress.
Thank you
Nicole McKenna
Operations Center
Type: Normal
Date: April 22, 2013
Day: Monday
Time: 6pm
Building(s): E23
Room(s): 1st Floor
System: Smoke Detectors
Duration: 10 hours per day
Reason:
For construction dust and all general construction related activities
Effect:
Loss of fire alarm system. The Safety Office will be advised of this and notify the Fire Department.