[168638] in Hotline Meeting
Bldg. E25-Fls. 2 thru 6 - RTU's 1,2,3,4 Supply and Exhaust Air Shutdown Flrs 2 thru 6 incl. fume hoods
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Apr 29 08:50:55 2013
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jennygar@MIT.EDU>, <biss@MIT.EDU>
Date: Mon, 29 Apr 2013 08:50:47 -0400
Message-ID: <B0F6313DA2C6402EA4E441721ECC5E29@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following RTU's 1,2,3,4 Supply and Exhaust Air Shutdown Flrs 2 thru 6 incl. fume hoods for Bldg. E25 is on Thursday, May 2, 2013 from 12:01AM til 6:00am is for your information and approval. Any questions please contact Billy Homeyer x8-0432.
Would you please let us know if this does or does not have your approval.
Thank you,
Jennifer M. Garland
Repair and Maintenance
4-4350
Type: Normal
Date: May 2, 2013
Day: Thursday
Time: 12:01am til 6:00am
Building(s): E25
Room(s): 2nd fl thru 6th floor
System: supply ventilation, cooling, laboratory exhaust
Duration: 12:01am til 6:00am
Reason:
We request bldg E25-RTU's 1, 2, 3, 4 shutdowns from 12:01 AM to 6 AM on Thursday morning, May 2nd, 2013 (report Wednesday night 5/1) for CP Blouin (Rob Venuti 603-231-0003) rerouting existing supply air ducts in the penthouse and tying-in 2 new lab supply air phoenix valves as part of the E25-6th floor Prof McGee Lab cleanroom project by DC Beane (Ryan Kucinski 617-997-9498). Paul Murphy 4-6361 and Biss Teelucksingh 2-5972 are the MIT project managers.
Animal quarters is not affected. Labs and offices on floors 2 thru 6 will be without supply/exhaust air, hood exhaust during the shutdown.
***E25 researchers should close hood sashes as they leave on Wednesday 5/1***
Effect:
Loss of supplky ventilation, cooling, laboratory exhaust for the duration of this shutdown.