[16343] in Hotline Meeting
Bldg 39, June 10
daemon@ATHENA.MIT.EDU (hykim@Athena.MIT.EDU)
Tue Jun 8 14:09:27 1993
From: hykim@Athena.MIT.EDU
To: shutdowns@MIT.EDU
Date: Tue, 08 Jun 93 14:09:14 EDT
Leanne from Op Center called with a shutdown to occur on Thurs, June 10 from
6:30 to 6:40 am. The air handler fans 1 and 3 in bldg 39 will be shutdown for
a period of 5 minutes each. Air handler fan 1 affects the bldg 39-301 wast and
the clean rooms. Air handler fan 3 affectrs the bldg 39 west offices and the
5th floor labs.
Susan Kim
Network Help Desk