[160717] in Hotline Meeting
*Extended - Bldg. 9 - All, Fire Alarm Shutdown Notification and
daemon@ATHENA.MIT.EDU (Janine Findlay)
Thu Aug 2 09:26:58 2012
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "cdh@mit.edu" <cdh@mit.edu>, "craze@mit.edu" <craze@mit.edu>,
"Jim
Harrington" <lordjim@mit.edu>, "laugh@mit.edu" <laugh@mit.edu>,
"OPS RM
Campus Services Main" <rm-mcs@mit.edu>,
Ops Custodial Admin & Support Staff
<cust-staff@mit.edu>,
"jrmac@mit.edu" <jrmac@mit.edu>, "annm@mit.edu"
<annm@mit.edu>,
"lthoma@MIT.EDU" <lthoma@mit.edu>,
"mvieira@mit.edu"
<mvieira@mit.edu>,
"kyegian@MIT.EDU" <kyegian@mit.edu>,
"shutdowns@mit.edu"
<shutdowns@mit.edu>,
"whomeyer@mit.edu" <whomeyer@mit.edu>,
"wradochi@mit.edu" <wradochi@mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>
CC: "jcombs@mit.edu" <jcombs@mit.edu>
Date: Thu, 2 Aug 2012 09:26:53 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CEB7C3CAE@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following *extended fire alarm shutdown notification and *live audible testing request for Bldg. 9 - All, on Thursday, August 2, 2012, 6:00am - 9:00am, *to also include Friday, August 3, 2012, 6:00am - 9:00am, is for your information and response. Any questions, please contact Billy Homeyer, x8-0432.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: August 2, 2012
Day: Thursday *and Friday
Time: 6:00am - 9:00am
Building(s): 9
Room(s): All
System: Fire Alarm and *Live audible Testing
Duration: 3 hours/3 hours
Reason:
Reilly Electric (Rob Bedard 508-962-1804) will be sounding the new bldg 9 fire alarm system between 6 AM and 9 AM on Thursday morning, August 2nd in order to test. The system is currently standing alone and will not report to the MIT Operations Center. MIT Fire is not required but approval from bldg 9 is, thank you, Billy H. 8-0432
*Extended - Dear all, RELCO did not complete testing this morning and we'd like to know if we could continue testing tomorrow morning, Friday 8/3 from 6 AM to 9 AM as well, Billy H. 8-0432
Effect:
Loss of fire alarms and *live audible testing for the duration of the shutdown.