[160695] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg E15 - 2nd Floor, Sprinkler Shutdown Notification

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Wed Aug 1 12:35:27 2012

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <pisanin@MIT.EDU>
Date: Wed, 1 Aug 2012 12:35:20 -0400
Message-ID: <A51046CA636049F999FF686171B5ED3E@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following sprinkler shutdown notification for Bldg E15 - 2nd floor on Thursday, August 2, 2012, from 7:00am - 2:00pm, is for your information. No response is required to this notification. Any questions please contact Billy Homeyer X.8-0432

We appreciate your patience while the repairs/renovations are in progress.

Thank you,

Chris Gilbert
Operations Center

The Safety Office will be advised of this and notify the Fire Department.


Type: Normal
Date: August 2, 2012
Day: Thursday
Time: 7:00am-2:00pm
Building(s): E15
Room(s): 2nd floor 
System: fire protection water 
Duration: 7 hours 
Reason: 
Relocate existing and add new sprinkler heads in the E15-201/205 construction areas. 

Effect: 
Loss of Fire Protection Water. 