[160691] in Hotline Meeting
FW: Extended Bldg. E25-Basement/1st Floor Smoke Detector/Vesda
daemon@ATHENA.MIT.EDU (Christopher Gilbert)
Wed Aug 1 12:07:46 2012
From: Christopher Gilbert <cgilbert@plant.mit.edu>
To: "jdoughty@mit.edu" <jdoughty@mit.edu>, "swade@mit.edu" <swade@mit.edu>,
"bbrown@mit.edu" <bbrown@mit.edu>, "jmganno@MIT.EDU" <jmganno@mit.edu>,
"jstatile@mit.edu" <jstatile@mit.edu>,
"rmarini@mit.edu" <rmarini@mit.edu>,
"colonero@mit.edu" <colonero@mit.edu>,
"kayser@mit.edu" <kayser@mit.edu>, "craigp@MIT.EDU" <craigp@mit.edu>,
OPS RM Campus Services East
<rm-ecs@mit.edu>,
Ops Custodial Admin & Support Staff <cust-staff@mit.edu>,
"srolph@MIT.EDU" <srolph@mit.edu>, "smaram@mit.edu" <smaram@mit.edu>,
"adaz@mit.edu" <adaz@mit.edu>, "jsbanks@mit.edu" <jsbanks@mit.edu>,
"ninadm@mit.edu" <ninadm@mit.edu>, "dgeraci@mit.edu" <dgeraci@mit.edu>,
Michael Smith <masmith@mit.edu>, "willer@mit.edu" <willer@mit.edu>,
"awolpert@mit.edu" <awolpert@mit.edu>,
"brig@med.mit.edu" <brig@med.mit.edu>,
"wayneb@mit.edu" <wayneb@mit.edu>,
MIT Schedules Office <schedules@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"barnard@mit.edu" <barnard@mit.edu>,
"monaglek@MIT.EDU" <monaglek@mit.edu>,
"bengel@mit.edu" <bengel@mit.edu>, "tquinn@mit.edu" <tquinn@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
"whomeyer@mit.edu" <whomeyer@mit.edu>,
"shutdowns@mit.edu"
<shutdowns@mit.edu>,
"whomeyer@mit.edu" <whomeyer@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
DOF Customer Service Center
<dof-csc@mit.edu>,
Ops RM Fire Protection Team <rm-fire-prot-team@mit.edu>,
"Francis K. Higson" <fhigson@plant.mit.edu>,
Gerhard Sinani
<sinanig@plant.mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
"DOF
Customer Service Center" <dof-csc@mit.edu>,
Ops RM Fire Protection Team
<rm-fire-prot-team@mit.edu>
Date: Wed, 1 Aug 2012 12:07:41 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CEB7C38B8@dof-exchmbx01.facilities.ms.mit.edu>
In-Reply-To: <4EEA516695C10541B7CB963FF54A56AF0CEB7C38A2@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following extended smoke detector/vesda, shutdown notification for Bldg. E25-Basement/1st Floor on Monday, March 19, 2012 though Monday, August, 6, 2012 from 6am to 2:00pm, regular work days (and to include Saturday, August 4, 2012,) is for your information. No response required to this notification. Any question please contact Bill Homeyer @ 8-0432
We appreciate your patience while the repairs/renovations are in progress.
Thank you,
Chris Gilbert
Operations Center
Type: Normal
Date: March 19, 2012
Day: Monday
Time: 6am
Building(s): E25
Room(s): Basement/1st Floor
System: Smoke Detectors/Vesda
Duration: 8 hours each day
Reason:
Precautionary shutdown for construction dust as part of the E25 basement renovation project.
Effect:
Loss of fire alarm system. The Safety Office will be advised of this and notify the Fire Department.