[160687] in Hotline Meeting
Bldg 13 - 3rd Floor, Sprinkler Shutdown Notification
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Wed Aug 1 11:09:12 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <biss@MIT.EDU>
Date: Wed, 1 Aug 2012 11:09:05 -0400
Message-ID: <DCEA30D8F269499B8156FD8A5BFEFC80@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following Sprinkler shutdown notification for Bldg 13 - 3rd Floor, on Friday, August 3, 2012, from 6:00am-2:00pm, is for your information. No response is required to this notification. Any questions please contact Billy Homeyer X.8-0432
We appreciate your patience while the repairs/renovations are in progress.
Thank you,
Chris Gilbert
Operations Center
The Safety Office will be advised of this and notify the Fire Department.
Type: Normal
Date: August 3, 2012
Day: Friday
Time: 6:00am-2:00pm
Building(s): 13
Room(s): 3rd floor
System: Fire Protection Water
Duration: 8 hours
Reason:
Tie-in new sprinkler piping in 3024 and change-out sprinkler heads in 3144.
Effect:
loss of sprinklers on the 3rd floor.