[160672] in Hotline Meeting
Bldg W1 - 1st Floor, Sprinkler Shutdown Notification
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Wed Aug 1 10:02:19 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <twanat@MIT.EDU>
Date: Wed, 1 Aug 2012 10:02:11 -0400
Message-ID: <60F50C3ADDC54D5BB9237AB4DB5E3453@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following sprinkle shutdown notification for Bldg W1 - first floor, on Friday, August 3, 2012, from 6:00am-11:00am is for your information. No response is required to this notification. Any questions, please contact Billy Homeyer, 8-0432
We appreciate your patience while the repairs/renovations are in progress.
Thank you
Chris Gilbert
Operations Center
The Safety Office will be advised of this and notify the Fire Department.
Type: Normal
Date: August 3, 2012
Day: Friday
Time: 6:00am-11:00am
Building(s): W1
Room(s): 1st floor
System: fire protection water
Duration: 5 hours
Reason:
Cannistraro to replace a leaking sprinkler head in room 1091 as part of the W1 renovation project.
Effect:
Loss of fire protection water to the first floor.