[160575] in Hotline Meeting
Bldg. 24 - 2nd Floor, Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Jul 30 13:26:02 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <kims@MIT.EDU>
Date: Mon, 30 Jul 2012 13:25:57 -0400
Message-ID: <BB9950A27BE1477ABA3F6A3D036529EF@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following chilled water shutdown request for Bldg. 24 - 2nd Floor, on Wednesday, August 1, 2012, 5:00am - 9:00am, is for your information and response. Any questions, please contact Billy Homeyer, x8-0432.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: August 1, 2012
Day: Wednesday
Time: 5:00am - 9:00am
Building(s): 24
Room(s): 2nd Floor
System: Chilled Water
Duration: 4 hours
Reason:
We request a bldg 24-2nd floor hilled water shutdown from 5 AM to 9 AM on Wednesday, August 1st, 2012 for AHC Mechanical (Al Cairns 781-844-7817) to install isolation valves off the mains in the hallway for a new fan coil unit being installed in office suite 24-220 as part of a renovation here for Nuclear Sci&Eng by MetroWest Construction (Art Alfano 781-706-9705). Kim Sutherland 8-5962 is the MIT project manager.
Effect:
Loss of chilled water and supply cooling air for the duration of the shutdown.