Approved Bldg. 10-4th Floor Sprinkler Shutdown Notification

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Jul 30 12:04:04 2012

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jcombs@MIT.EDU>
Date: Mon, 30 Jul 2012 12:03:57 -0400
Message-ID: <E9696F81352443A7AE4BF1051A49F4FA@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following sprinkler shutdown notification for Bldg. 10 - 4th Floor on Tuesday, July 30, 2012 from 6am to 2pm is for your information. No response required to this notification. Any question please contact Billy Homeyer @ 8-0432

We appreciate your patience while the repairs/renovations are in progress.

Thank you
Bill Lombard
Operations Center


Type: Normal
Date: July 30, 2012
Day: Tuesday
Time: 6am
Building(s): 10
Room(s): 4th Floor
System: Fire Protection Water
Duration: 8 hours
Reason: 
Relocate 4th floor piping to make-way for new duct work

Effect: 
Loss of fire protection water. The Safety Office will be advised of this and notify the Fire Department.