[160415] in Hotline Meeting
Approved Bldg. N51 and N52 - All, Natural Gas Shutdown
daemon@ATHENA.MIT.EDU (Janine Findlay)
Wed Jul 25 13:55:42 2012
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "shutdowns@mit.edu" <shutdowns@mit.edu>,
"whomeyer@mit.edu"
<whomeyer@mit.edu>,
Ops RM Plumbing Team <rm-plumbing@mit.edu>,
"sstcroix@mit.edu" <sstcroix@mit.edu>, "cavs@mit.edu" <cavs@mit.edu>,
"cbdewart@mit.edu" <cbdewart@mit.edu>,
Jim Harrington <lordjim@mit.edu>, "laugh@mit.edu" <laugh@mit.edu>,
"Bales@mit.edu" <Bales@mit.edu>, "sgtist@mit.edu" <sgtist@mit.edu>,
"slipnosk@mit.edu" <slipnosk@mit.edu>,
"sstcroix@mit.edu" <sstcroix@mit.edu>, "bobk@mit.edu" <bobk@mit.edu>,
"nmorriso@MIT.EDU" <nmorriso@mit.edu>,
OPS RM Campus Services West
<rm-wcs@mit.edu>,
"jdurant@mit.edu" <jdurant@mit.edu>, "mleen@mit.edu"
<mleen@mit.edu>,
"majetich@mit.edu" <majetich@mit.edu>,
"dstidsen@mit.edu"
<dstidsen@mit.edu>,
"ronnc@mit.edu" <ronnc@mit.edu>, "emlayne@mit.edu"
<emlayne@mit.edu>,
"apetroff@MIT.EDU" <apetroff@mit.edu>,
"semo-admin@mit.edu" <semo-admin@mit.edu>,
"barnard@mit.edu"
<barnard@mit.edu>,
"monaglek@MIT.EDU" <monaglek@mit.edu>,
"alvarso@mit.edu"
<alvarso@mit.edu>,
"tmrc-officers@mit.edu" <tmrc-officers@mit.edu>,
"quentin@mit.edu" <quentin@mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
DOF Customer Service Center
<dof-csc@mit.edu>,
Ops Custodial Admin & Support Staff <cust-staff@mit.edu>
CC: "pjmurphy@mit.edu" <pjmurphy@mit.edu>
Date: Wed, 25 Jul 2012 13:55:37 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CEB53DBBF@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved natural gas shutdown for Bldg. N51 and N52 - All, on Thursday, July 26, 2012, 6:00am through 2:00pm on Friday, July 27, 2012, is for your information. Any questions, please contact Paul Murphy, x4-6163.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: July 26, 2012
Day: Thursday
Time: 6:00am (7/26) through 2:00pm (7/27)
Building(s): N51 and N52
Room(s): All
System: Natural Gas
Duration: 32 hours
Reason:
We request a bldg N52-all natural gas shutdown from 6 AM on Thursday, July 26th to 2 PM on Friday, July 27th, 2012 for AHC Mechanical (Al Cairns 781-844-7817) to install gas meters at the two new boilers as part of phase 2 of the boiler replacement project. Paul Murphy 4-6163 is the MIT project manager.
The 3rd floors of N521/N52 DLab/SUTD will be without comfort cooling from the new rooftop gas fired airhandling unit and the bldgs will be without hot - hot water and other heating during the shutdown period.
Effect:
Loss of domestic hot water, heating hot water, supply heating and cooling air as noted above, and low pressure steam for the duration of the shutdown.