[160415] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Approved Bldg. N51 and N52 - All, Natural Gas Shutdown

daemon@ATHENA.MIT.EDU (Janine Findlay)
Wed Jul 25 13:55:42 2012

From: Janine Findlay <jfindlay@plant.mit.edu>
To: "shutdowns@mit.edu" <shutdowns@mit.edu>,
        "whomeyer@mit.edu"
	<whomeyer@mit.edu>,
        Ops RM Plumbing Team <rm-plumbing@mit.edu>,
        "sstcroix@mit.edu" <sstcroix@mit.edu>, "cavs@mit.edu" <cavs@mit.edu>,
        "cbdewart@mit.edu" <cbdewart@mit.edu>,
        Jim Harrington <lordjim@mit.edu>, "laugh@mit.edu" <laugh@mit.edu>,
        "Bales@mit.edu" <Bales@mit.edu>, "sgtist@mit.edu" <sgtist@mit.edu>,
        "slipnosk@mit.edu" <slipnosk@mit.edu>,
        "sstcroix@mit.edu" <sstcroix@mit.edu>, "bobk@mit.edu" <bobk@mit.edu>,
        "nmorriso@MIT.EDU" <nmorriso@mit.edu>,
        OPS RM Campus Services West
	<rm-wcs@mit.edu>,
        "jdurant@mit.edu" <jdurant@mit.edu>, "mleen@mit.edu"
	<mleen@mit.edu>,
        "majetich@mit.edu" <majetich@mit.edu>,
        "dstidsen@mit.edu"
	<dstidsen@mit.edu>,
        "ronnc@mit.edu" <ronnc@mit.edu>, "emlayne@mit.edu"
	<emlayne@mit.edu>,
        "apetroff@MIT.EDU" <apetroff@mit.edu>,
        "semo-admin@mit.edu" <semo-admin@mit.edu>,
        "barnard@mit.edu"
	<barnard@mit.edu>,
        "monaglek@MIT.EDU" <monaglek@mit.edu>,
        "alvarso@mit.edu"
	<alvarso@mit.edu>,
        "tmrc-officers@mit.edu" <tmrc-officers@mit.edu>,
        "quentin@mit.edu" <quentin@mit.edu>,
        Ops RM Shutdown <rm-shutdown@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        DOF Customer Service Center
	<dof-csc@mit.edu>,
        Ops Custodial Admin & Support Staff <cust-staff@mit.edu>
CC: "pjmurphy@mit.edu" <pjmurphy@mit.edu>
Date: Wed, 25 Jul 2012 13:55:37 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CEB53DBBF@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following approved natural gas shutdown for Bldg. N51 and N52 - All, on Thursday, July 26, 2012, 6:00am through 2:00pm on Friday, July 27, 2012, is for your information.  Any questions, please contact Paul Murphy, x4-6163.

Thank you,

Jani Findlay
Repair and Maintenance
x3-6381

Type: Normal
Date: July 26, 2012
Day: Thursday
Time: 6:00am (7/26) through 2:00pm (7/27)
Building(s): N51 and N52
Room(s): All
System: Natural Gas
Duration: 32 hours
Reason: 
We request a bldg N52-all natural gas shutdown from 6 AM on Thursday, July 26th to 2 PM on Friday, July 27th, 2012 for AHC Mechanical (Al Cairns 781-844-7817) to install gas meters at the two new boilers as part of phase 2 of the boiler replacement project. Paul Murphy 4-6163 is the MIT project manager.

The 3rd floors of N521/N52 DLab/SUTD will be without comfort cooling from the new rooftop gas fired airhandling unit and the bldgs will be without hot - hot water and other heating during the shutdown period.

Effect: 
Loss of domestic hot water, heating hot water, supply heating and cooling air as noted above, and low pressure steam for the duration of the shutdown.