[160373] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Approved Bldg.13 - Rooms 2128, 2132, 2144, 3124, 3136, 3138, 3144,

daemon@ATHENA.MIT.EDU (Janine Findlay)
Tue Jul 24 11:15:57 2012

From: Janine Findlay <jfindlay@plant.mit.edu>
To: "Leskolo@mit.edu" <Leskolo@mit.edu>,
        OPS RM Campus Services Main
	<rm-mcs@mit.edu>,
        Ops Custodial Admin & Support Staff <cust-staff@mit.edu>,
        "jbartels@MIT.EDU" <jbartels@mit.edu>,
        "mbulsara@mit.edu" <mbulsara@mit.edu>,
        "sdalton@MIT.EDU" <sdalton@mit.edu>,
        "jeileef@mit.edu" <jeileef@mit.edu>, "elk@MIT.EDU" <elk@mit.edu>,
        "eafitz@MIT.EDU" <eafitz@mit.edu>,
        "gillooly@MIT.EDU" <gillooly@mit.edu>,
        "wayneb@mit.edu" <wayneb@mit.edu>,
        "MIT Schedules Office" <schedules@mit.edu>,
        "jingkong@mit.edu"
	<jingkong@mit.edu>,
        "barnard@mit.edu" <barnard@mit.edu>,
        "monaglek@MIT.EDU"
	<monaglek@mit.edu>,
        "shutdowns@mit.edu" <shutdowns@mit.edu>,
        Billy Homeyer
	<whomeyer@plant.mit.edu>,
        Ops RM Shutdown <rm-shutdown@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        DOF Customer Service Center
	<dof-csc@mit.edu>,
        Ops Custodial Admin & Support Staff <cust-staff@mit.edu>,
        Ops RM Electrical Controls Team <rm-elecctl@mit.edu>,
        "rlucas@mit.edu"
	<rlucas@mit.edu>, "dcrovo@mit.edu" <dcrovo@mit.edu>
CC: "biss@mit.edu" <biss@mit.edu>
Date: Tue, 24 Jul 2012 11:15:53 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CEB53D5FB@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following approved normal (208V/120V) building power shutdown for Bldg.13 - Rooms 2128, 2132, 2144, 3124, 3136, 3138, 3144, 4123, 4124, 4136, 4139, 5127, 5128, 5132 and 5140, on Wednesday, July 25, 2012, 12:01am - 6:00am,  is for your information. Any questions please contact Billy Homeyer x8-0432.

Thank you,

Jani Findlay
Repair and Maintenance
X3-6381

Type: Normal
Date: July 25, 2012
Day: Wednesday
Time: 12:01am - 6:00am
Building(s): 13
Room(s): 2128, 2132, 2144, 3124, 3136, 3138, 3144, 4123, 4124, 4136, 4139, 5127, 5128, 5132 and 5140.
System: Normal Bldg. Power
Duration: 6 hours
Reason: 
We request a bldg 13 normal 208V/120V power shutdown from 12:01 AM to 6 AM on Wednesday morning July 25, for Bennett Electric to install and tie-in a new 100A circuit breaker in power panel 41C located in 13-3136Z (core G) for a new sub panel being installed in 3144. Feeder 215 needs to be shutdown and the following labs or offices will be without normal power during the shutdown; 2128, 2132, 2144, 3124, 3136, 3138, 3144, 4123, 4124, 4136, 4139, 5127, 5128, 5132 and 5140. No fume hood exhaust air will be affected in these areas however the lights in the hoods and the hood electrical outlets will be.

Effect: 
Feeder 215 needs to be shutdown and the following labs or offices will be without normal power during the shutdown; 2128, 2132, 2144, 3124, 3136, 3138, 3144, 4123, 4124, 4136, 4139, 5127, 5128, 5132 and 5140. No fume hood exhaust air will be affected in these areas however the lights in the hoods and the hood electrical outlets will be. 