W71 - All Emergency & Normal Power shutdown request

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu Jul 12 10:03:00 2012

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <shutdowns@MIT.EDU>, <whomeyer@plant.mit.edu>, <sgilliga@MIT.EDU>
Date: Thu, 12 Jul 2012 10:02:57 -0400
Message-ID: <972AF4D4ED9C4D0B8D2B3B7A625D4B48@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Emergency & Normal Power shutdown request for Bldg. W71-All on Friday, July 13, 2012 is for your information and response. Any questions please contact Billy Homeyer x8-0432.

Would you please let us know whether this does or does not have your approval.

Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938


We request bldg W71-all normal and emergency power shutdowns on Friday, July 13th, 2012 as follows; emergency power from 6 AM to 10 AM for J. & M. Brown Co (Bob Cataldo 617-592-1564) to remove the emergency power feed to the auto transfer switch and install a new 
emergency power panel for life-safety/fire alarm systems; and a bldg all normal power shutdown from 1 PM to 2 PM for JMBCo to remove the normal power feed to the ATS and remove the fire pump feed which is tapped off the buss between the 13.8KV-480V transformer and the substation main (fire pump is being demo'd - system gets fed from west campus fire main) and as part of the bldg W71 life-safety upgrades project by Shawmut Construction (Tom Ploude 781-983-3850), Keith Diggans 4-6174 is the MIT project manager, John Engle 4-5001 is covering.

Type: Normal
Date: July 13, 2012
Day: Friday
Time: 6:00am 10:00am (emerg) 1:00pm - 2:00pm (normal)
Building(s): W71
Room(s): All
System: Emergency Power and Normal Power
Duration: 4 hours (emerg) 1 hours (normal
Reason: 
To demo the generator/fire pump auto transfer switch, demo the fire pump.

Effect: 
Loss of emergency power 6:00am - 10:00am and loss of normal power 1:00pm - 2:00pm.