Asbestos Abatement Notification - Bldg. 4 - 403 & 403A
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu Jul 12 06:50:10 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <cp-command@MIT.EDU>, <safety@MIT.EDU>, <Operators@plant.mit.edu>,
<dof-csc@MIT.EDU>, <plant-asbestos@MIT.EDU>,
<generalmail@asbestos.com>, <shutdowns@MIT.EDU>
Date: Thu, 12 Jul 2012 06:49:45 -0400
Message-ID: <D122C71839374C85832D366554FF8F7C@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
This is to notify you of the abatement of approximately 75 linear feet of asbestos pipe insulation from Bldg. 4 room 403 and 403A. We will have an outside consultant monitor air quality on Thursday, July 12, 2012 @ 7:00am thur Friday, July 13, 2012 at 3:00pm. Any questions, please contact Nicole Pisani 617-715-5157.
We apologize for any inconvenience this may cause you.
Thank you,
Bernadette Drinkwater
Repair and Maintenance
x3-0938
Type: Normal
Date: July 12, 2012
Day: Thursday
Time: 7:00am (Thurs.) - 3:00pm (Fri)
Building(s): 4
Room(s): 403 & 403A
System: None
Duration: 32 hours
Reason:
Approximatel 75 linear feet of asbestos pipe.
Effect:
There will be no access to this area during the abatement.