Bldg 4-403/403A Sprinkler Shutdown Notification

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Wed Jul 11 14:37:47 2012

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <pisanin@MIT.EDU>
Date: Wed, 11 Jul 2012 14:37:36 -0400
Message-ID: <9E5EA309904642259DA2B24C5D9C5F5B@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following Sprinkler shutdown notification for building 4-403/403A on Thursday, July 12, 2012, and Friday July 13, 2012 from 7:00am until 3:00pm is for your information. No response is required to this notification. Any questions, please contact Billy Homeyer X.8-0432

We appreciate your patience while the repairs/renovations are in progress.

Thank you,

Chris Gilbert
Operations Center

The Safety Office will be advised of this and notify the Fire Department.


Type: Normal
Date: July 12, 2012
Day: Thursday
Time: 7:00am-3:00pm 
Building(s): 4
Room(s): 403/403A
System: Fire Protection Water 
Duration: 8 hours 
Reason: 
Asbestos pipe insulation removal in area. 

Effect: 
Loss of fire protection water. 