[160014] in Hotline Meeting
Bldg. 62 and 64 - all, Emergency Building Power and Lighting Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue Jul 10 12:40:18 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <rlucas@MIT.EDU>
Date: Tue, 10 Jul 2012 12:40:15 -0400
Message-ID: <360732022EA84A3F915DCDC2DC9A0C36@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following emergency building power and lighting shutdown request for Bldg. 62 and 64 - All, on Friday, July 13 and Friday, July 20, 2012, 10:00am - 11:00am each day, is for your information and response. Any questions, please contact Rich Lucas, x4-6801.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: July 13, 2012
Day: Friday
Time: 10:00am - 11:00am
Building(s): 62 and 64
Room(s): All
System: Emergency Building Power and Lighting
Duration: 1 hour/day
Reason:
A shutdown of Emergency Power is required in building 62 & 64 so we can hook up an alternate source of power for the week long shutdown of bldg. 62 & 64.
This emergency power shutdown should not last longer an hour and the normal power will not be affected. Only buildings 62 & 64 will lose Emergency Power.
Shutdown 1: Friday, July 13, 10 to 11 AM.
Shutdown 2: Friday, July 20, 10 to 11 AM.
Effect:
Loss of emergency generator, emergency building power, elevators, computers, telephones, lighting (including corridor and stairs), general/toilet exhaust, fire alarms for the duration of the shutdown.