Bldg. E17-1st Floor, E18-All, and E19-2nd Floor (new area) and 5th Floor - Air Handler Unit 2, 8, 9, & 10 Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Fri Jul 6 09:44:16 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jcollins@MIT.EDU>
Date: Fri, 6 Jul 2012 09:44:03 -0400
Message-ID: <F4055BD5D1F3409DA2D12E59C0050578@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following air handler units 2, 8, 9, & 10 shutdown request for Bldg. E17-1st Floor, E18-All, and E19-2nd Floor (new area) and 5th Floor, on Friday, July 13, 2012, 6:00pm through 6:00am on Monday, July 16, 2012, is for your information and response. Any questions, please contact Joe Collins, x3-3621.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: June 13, 2012
Day: Friday
Time: 6:00pm (7/13) through 6:00am (7/16)
Building(s): E17, E18, & E19
Room(s): Bldg. E17-1st Floor, E18-All, and E19-2nd Floor (new area) and 5th Floor
System: Air Handler Units 2, 8, 9, & 10
Duration: 60 hours
Reason:
We request a Building E19 Air Handling Unit numbers 2, 8 ,9 & 10 shutdown on Friday July 13th from 6:00pm until Monday July 16th at 6:00am to tie in ductwork to feed IS&T 1st floor office in E17. Barr & Barr (Dick Akins 774-281-0162) will be removing AHU 2 (Also known as AC2) out of service, the PM tag number will follow for decommissioning the unit. The Chemistry group on the 5th floor of E19 currently uses AHU 8, 9, & 10 which will be shutdown during this timeframe. The air handling unit that feeds the IS&T group on the 1st floor of E17 will also be down during this timeframe while we reconnect. This is part of the E17-E18 renovation project. MIT Project Managers are Joe Collins 3-3621 and Jan Burke 8-5463.
Effect:
Loss of supply ventilation air for the duration of the shutdown.