[159843] in Hotline Meeting
Bldg. E19 - 6th and 7th Floor Offices, Heating Hot Water Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Jul 2 13:15:03 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <jcollins@MIT.EDU>, <janb@MIT.EDU>
Date: Mon, 2 Jul 2012 13:14:54 -0400
Message-ID: <A0345A18304940EDA7334B40B95DEE44@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following heating hot water shutdown request for Bldg. E19 - 6th and 7th Floor Offices, on Thursday, July 5, 2012, 5:00am - 2:30am, is for your information and response. Any questions, please contact Joe Collins, x3-3621.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: July 5, 2012
Day: Thursday
Time: 5:00am - 2:30am
Building(s): E19
Room(s): 6th and 7th Floor Offices
System: Heating Hot Water
Duration: 9-1/2 hours
Reason:
We request a Building E19 heating hot water shutdown on Thursday July 5th from 5:00am until 2:30pm for Barr & Barr (Dick Akins 774-281-0162) to cut and cap piping that feeds E18 renovation area. This is part of the E17-E18 renovation project. MIT Project Managers are Joe Collins 3-3621 and Jan Burke 8-5463.
Effect:
Loss of heating hot water for the duration of the shutdown.