Bldg. NW21 - 2nd Floor, Normal 120V Building Power Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Fri Jun 29 14:16:42 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <billvit@MIT.EDU>
Date: Fri, 29 Jun 2012 14:16:39 -0400
Message-ID: <F91698347178459880D6070D195248C0@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following normal 120V building power shutdown request for Bldg. NW21 - 2nd Floor, on Tuesday, July 3, 2012, 5:00am - 7:00am, is for your information and response. Any questions, please contact Bill Vitkosky, x3-6517.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: July 3, 2012
Day: Tuesday
Time: 5:00am - 7:00am
Building(s): NW21
Room(s): 2nd Floor
System: Normal 120V Building Power
Duration: 2 hours
Reason:
We request a bldg NW21-2nd floor normal bldg power shutdown, 120V/208V panel PPA-5, serving 2nd floor lighting and office outlets, a water heater and a copy machine from 5 AM to 7 AM on Tuesday, July 3rd, 2012 for JMBCo (Dale Blue 617-293-5103) installing circuit breakers and tying-in power for roof level lighting replacement fixtures as part of the NW21 structural repairs project by Shawmut Construction (Dan Cook 617-908-6990). Bill Vitkosky 3-3517 is the MIT project manager.
Effect:
Loss of building power, computers, telephones, and lighting for the duration of the shutdown.