Bldg. E62 - Basement through 6th Floor, Ventilation and Natural Gas Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Fri Jun 29 13:43:32 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <rpc@MIT.EDU>
Date: Fri, 29 Jun 2012 13:43:30 -0400
Message-ID: <27BAC32B98D24E34B6E337B2DADFB579@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following ventilation and natural gas shutdown request for Bldg. E62 - Basement through 6th Floor, on Saturday, July 7, 2012, 7:00am - 7:00pm, is for your information and response. Any questions, please contact Bob Cunkelman, x4-6162.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: July 7, 2012
Day: Saturday
Time: 7:00am - 7:00pm
Building(s): E62
Room(s): Basement through 6th Floor
System: Ventilation and Natural Gas
Duration: up to 12 hours
Reason:
to perform building pressurization test
Effect:
Loss of supply ventilation and cooling air, general/toilet exhaust, and natural gas for the duration of the shutdown.