Bldg. E15 - All Floors, East Side of building, Supply Cooling Air (AH-1)Shutdown Request

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Wed Jun 27 14:47:00 2012

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <mmcorrei@MIT.EDU>
Date: Wed, 27 Jun 2012 14:46:58 -0400
Message-ID: <335C8C4370E148BEA775339D36B2B556@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following supply cooling air shutdown request for Bldg. E15 - All Floors, East Side of building, on Friday, June 29, 2012, 9:00am - 3:00pm, is for your information and response.  Any questions, please contact Mike Correira, x8-9174.

Please let us know whether this does or does not have your approval.

Thank you,

Jani Findlay
Repair and Maintenance
x3-6381

Type: Normal
Date: June 29, 2012
Day: Friday
Time: 9:00am - 3:00pm
Building(s): E15
Room(s): All Floors, East Side of building,
System: Supply Cooling Air (AH-1)
Duration: 6 hours
Reason: 
to install new chilled water valve

Effect: 
Loss of supply cooling air for the east side of the building for the duration of the shutdown.