Approved Critical - Bldg. 9 - All, Domestic Hot Water Shutdown

daemon@ATHENA.MIT.EDU (Janine Findlay)
Wed Jun 27 14:32:03 2012

From: Janine Findlay <jfindlay@plant.mit.edu>
To: "cdh@mit.edu" <cdh@mit.edu>, "craze@mit.edu" <craze@mit.edu>,
        "Jim
 Harrington" <lordjim@mit.edu>, "laugh@mit.edu" <laugh@mit.edu>,
        "OPS RM
 Campus Services Main" <rm-mcs@mit.edu>,
        Ops Custodial Admin & Support Staff
	<cust-staff@mit.edu>,
        "jrmac@mit.edu" <jrmac@mit.edu>,
        "segaloff@MIT.EDU"
	<segaloff@mit.edu>,
        "gillooly@MIT.EDU" <gillooly@mit.edu>, "annm@mit.edu"
	<annm@mit.edu>,
        "dgeltner@mit.edu" <dgeltner@mit.edu>,
        "lthoma@MIT.EDU"
	<lthoma@mit.edu>,
        "mvieira@mit.edu" <mvieira@mit.edu>,
        "barnard@mit.edu"
	<barnard@mit.edu>,
        "monaglek@MIT.EDU" <monaglek@mit.edu>,
        "kyegian@MIT.EDU"
	<kyegian@mit.edu>,
        Ops RM Plumbing Team <rm-plumbing@mit.edu>,
        "shutdowns@mit.edu" <shutdowns@mit.edu>,
        Ops RM Shutdown
	<rm-shutdown@mit.edu>,
        "cp-command@mit.edu" <cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
        "DOF
 Customer Service Center" <dof-csc@mit.edu>,
        "Ops Custodial Admin & Support
 Staff" <cust-staff@mit.edu>
CC: "smchugh@mit.edu" <smchugh@mit.edu>,
        "mmcorrei@mit.edu"
	<mmcorrei@mit.edu>,
        Edward Rita <erita@plant.mit.edu>
Date: Wed, 27 Jun 2012 14:31:59 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE873EB65@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following approved critical domestic hot water shutdown for Bldg. 9 - All, on Thursday, June 28, 2012, 5:30am - 7:30am, is for your information.  Any questions, please contact Steve McHugh, x3-4948 and ask to have him paged.

Thank you,

Jani Findlay
Repair and Maintenance
x3-6381

Type: Critical
Date: June 28, 2012
Day: Thursday
Time: 5:30am - 7:30am
Building(s): 9
Room(s): All
System: Domestic Hot Water
Duration: 2 hours
Reason: 
to make critical repairs to leak running into the fire panel room

Effect: 
Loss of domestic hot water for the duration of the shutdown.