[159719] in Hotline Meeting
Approved Bldg. W4 - West side of building - Steam, Domestic Hot
daemon@ATHENA.MIT.EDU (Janine Findlay)
Wed Jun 27 12:34:36 2012
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "shutdowns@mit.edu" <shutdowns@mit.edu>,
Ops RM Piping Systems Team
<rm-pipesys@mit.edu>,
"mlbuck@mit.edu" <mlbuck@mit.edu>, "tommyl@mit.edu"
<tommyl@mit.edu>,
"myersm@MIT.EDU" <myersm@mit.edu>,
"OPS RM Campus Services
West" <rm-wcs@mit.edu>,
"src@MIT.EDU" <src@mit.edu>, "colins@mit.edu"
<colins@mit.edu>,
"hmgr@mit.edu" <hmgr@mit.edu>, "kcn@mit.edu" <kcn@mit.edu>,
"mwhelan@mit.edu" <mwhelan@mit.edu>,
"barnard@mit.edu" <barnard@mit.edu>,
"Ops RM Shutdown" <rm-shutdown@mit.edu>,
"cp-command@mit.edu"
<cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>,
Operators
<Operators@plant.mit.edu>,
"DOF Customer Service Center" <dof-csc@mit.edu>,
"Ops Custodial Admin & Support Staff" <cust-staff@mit.edu>
CC: "mmcorrei@mit.edu" <mmcorrei@mit.edu>
Date: Wed, 27 Jun 2012 12:34:32 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE873EAA3@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved steam, domestic hot water, heating hot water, and supply heating air shutdown for Bldg. W4 - West side of building, on Thursday, June 28, 2012, 9:00am - 3:00pm, is for your information. Any questions, please contact Mike Correira, x8-9174.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: June 28, 2012
Day: Thursday
Time: 9:00am - 3:00pm
Building(s): W4
Room(s): West side of building
System: Steam, Domestic Hot Water, Heating Hot Water, and Supply Heating Air
Duration: 6 hours
Reason:
to install new spence valve and safet valve
Effect:
Loss of domestic hot water, heating hot water, supply heating air, and steam for the duration of the shutdown.