Approved Bldg. 62 and 64 - All, Normal Building Power and Lighting
daemon@ATHENA.MIT.EDU (Janine Findlay)
Tue Jun 26 14:15:57 2012
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "shutdowns@mit.edu" <shutdowns@mit.edu>,
Ops RM Electrical Controls Team
<rm-elecctl@mit.edu>,
"dcrovo@mit.edu" <dcrovo@mit.edu>, "src@MIT.EDU"
<src@mit.edu>,
"colins@mit.edu" <colins@mit.edu>, "hmgr@mit.edu"
<hmgr@mit.edu>,
"kcn@mit.edu" <kcn@mit.edu>, "mwhelan@mit.edu"
<mwhelan@mit.edu>,
"gillooly@MIT.EDU" <gillooly@mit.edu>,
"barnard@mit.edu"
<barnard@mit.edu>,
"monaglek@MIT.EDU" <monaglek@mit.edu>,
Ops RM Shutdown
<rm-shutdown@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
"DOF
Customer Service Center" <dof-csc@mit.edu>,
"Ops Custodial Admin & Support
Staff" <cust-staff@mit.edu>
CC: "rlucas@mit.edu" <rlucas@mit.edu>
Date: Tue, 26 Jun 2012 14:15:16 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE873E67B@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved normal building power and lighting shutdown for Bldg. 62 and 64 - All, on Monday, July 16, 2012, at 6:00am through 4:00pm on Friday, July 20, 2012, is for your information. Any questions, please contact Rich Lucas, x4-6801.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: July 16, 2012
Day: Monday
Time: 6:00am (7/16) through 4:00pm (7/20)
Building(s): 62 and 64
Room(s): All
System: Normal Building Power and Lighting
Duration: 5 days
Reason:
Shutdown of All Normal Power & Lighting in Buildings 62 & 64 is requested in order to perform a major repair and PM of the Switchgear. This repair will take up to 5 days so I've worked out this schedule with Dennis Collins of Housing to have the building empty during this week. Shutdown would begin Monday 6:00 AM July 16 and continue until Friday 4:00 PM July 20.
Emergency Power will remain on during this shutdown.
The buildings should be empty during this time except for the Main Electrical room 62-001A.
Effect:
Loss of emergency generator, building power, elevators, computers, telephones, lighting (including corridors/stairs), supply ventilation/cooling air, general/toilet exhaust, storm drain/sanitary drainage, and smoke detectors (daily) for the duration of the shutdown.