[159688] in Hotline Meeting
Approved Bldg. 10-Basement Smoke Detector Shutdown Notification
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Tue Jun 26 12:28:16 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <rlanigan@MIT.EDU>
Date: Tue, 26 Jun 2012 12:27:52 -0400
Message-ID: <B224062C526D4119BDF8CE1D5D6F617A@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following smoke detector, shutdown notification for Bldg. 10-Basement on Wednesday, June 27, 2012 from 6am to 11am is for your information. No response required to this notification. Any question please contact Bob Lanigan @ 3-0312
We appreciate your patience while the repairs/renovations are in progress.
Thank you
Bill Lombard
Operations Center
Type: Normal
Date: June 27, 2012
Day: Wednesday
Time: 6am
Building(s): 10
Room(s): Basement
System: Smoke Detectors
Duration: 5 hours
Reason:
Contractor drilling near devices
Effect:
Loss of fire alarm system. The Safety Office will be advised of this and notify the Fire Department.