[159668] in Hotline Meeting
Approved Bldg. E25 - All Rooms on West Side, Normal Building Power
daemon@ATHENA.MIT.EDU (Janine Findlay)
Tue Jun 26 08:16:11 2012
From: Janine Findlay <jfindlay@plant.mit.edu>
To: Ops RM Shutdown <rm-shutdown@mit.edu>,
"cp-command@mit.edu"
<cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>,
Operators
<Operators@plant.mit.edu>,
DOF Customer Service Center <dof-csc@mit.edu>,
"Ops Custodial Admin & Support Staff" <cust-staff@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
Ops RM Electrical Controls Team
<rm-elecctl@mit.edu>,
"rlucas@mit.edu" <rlucas@mit.edu>, "dcrovo@mit.edu"
<dcrovo@mit.edu>,
"whomeyer@mit.edu" <whomeyer@mit.edu>,
"jdoughty@mit.edu"
<jdoughty@mit.edu>,
"swade@mit.edu" <swade@mit.edu>, "bbrown@mit.edu"
<bbrown@mit.edu>,
"jmganno@MIT.EDU" <jmganno@mit.edu>,
"jstatile@mit.edu"
<jstatile@mit.edu>,
"rmarini@mit.edu" <rmarini@mit.edu>,
"colonero@mit.edu"
<colonero@mit.edu>,
"kayser@mit.edu" <kayser@mit.edu>, "craigp@MIT.EDU"
<craigp@mit.edu>,
"OPS RM Campus Services East" <rm-ecs@mit.edu>,
Ops
Custodial Admin & Support Staff <cust-staff@mit.edu>,
"smaram@mit.edu"
<smaram@mit.edu>, "adaz@mit.edu" <adaz@mit.edu>,
"ninadm@mit.edu"
<ninadm@mit.edu>,
"dgeraci@mit.edu" <dgeraci@mit.edu>, Michael Smith
<masmith@mit.edu>,
"willer@mit.edu" <willer@mit.edu>,
"awolpert@mit.edu"
<awolpert@mit.edu>,
"brig@med.mit.edu" <brig@med.mit.edu>,
"wayneb@mit.edu"
<wayneb@mit.edu>,
MIT Schedules Office <schedules@mit.edu>,
"heatherg@mit.edu" <heatherg@mit.edu>,
"barnard@mit.edu" <barnard@mit.edu>,
"monaglek@MIT.EDU" <monaglek@mit.edu>,
"bengel@mit.edu" <bengel@mit.edu>, "tquinn@mit.edu" <tquinn@mit.edu>
CC: "jhimmel@mit.edu" <jhimmel@mit.edu>
Date: Tue, 26 Jun 2012 08:16:08 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE873E3DF@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved normal building power (208V/120V) shutdown for Bldg. E25 - All Rooms on West Side (all floors - room numbers greater than *29), Friday, June 29, 2012, 4:00am - 8:00am, is for your information. Any questions, please contact Billy Homeyer, x8-0432.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: June 29, 2012
Day: Friday
Time: 4:00am - 8:00am
Building(s): E25
Room(s): All Rooms on West Side (all floors - room numbers greater than *29)
System: Normal Building Power (208V/120V)
Duration: 4 hours
Reason:
We request a bldg E25-208V/120V normal power normal bldg power shutdown affecting rooms with room numbers greater than X29 (E25-230 and above, 330 and above etc) for EG Sawyer to tie-in new 480V cabling from the electrical substation in E23-008E to the E25 west riser transformer (this is the replacement of the damaged cable) and as part of the E25-AQ's renovation project by Bond Brothers (Andy Cogliano 617-839-8965). Jon Himmel 2-2402 is the MIT project manager.
Note* during the last scheduled power shutdown in March the cables from the substation where run to an overhead can and made safe; the breaker was racked out. We will make connections in this can via compression fittings and when done, rack in the breaker. There is no need for a full substation shutdown this time, only the E25 west riser.
Effect:
Loss of building power, computers, telephones, and lighting for the duration of the shutdown.