Bldg. 31 - All, High Pressure Steam, Heating Hot Water, Domestic Hot Water, and Lab Process Hot Water, Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Jun 25 14:03:39 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <vcrayton@MIT.EDU>
Date: Mon, 25 Jun 2012 14:03:36 -0400
Message-ID: <318A2FA643754B09A93D5449283951DC@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following high pressure steam, heating hot water, domestic hot water, and lab process hot water shutdown request for Bldg. 31 - All, on Wednesday, June 27, 2012, 7:00am - 1:00pm, is for your information and response. Any questions, please contact Vaughn Crayton, x3-5898.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: June 27, 2012
Day: Wednesday
Time: 7:00am - 1:00pm
Building(s): 31
Room(s): All
System: High Pressure Steam, Heating Hot Water, Domestic Hot Water, and Lab Process Hot Water
Duration: 6 hours
Reason:
to install a new isolation valve for the high pressure steam to the new steam station
Effect:
Loss of domestic hot water, lab process hot water, heating hot water, supply heating air, high/medium/low pressure steam, and condensate return for the duration of the shutdown.