[159653] in Hotline Meeting
Bldg. NW12 - All, Main Electrical System (Normal Power and Lighting) Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Jun 25 09:58:09 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <rlucas@MIT.EDU>
Date: Mon, 25 Jun 2012 09:58:02 -0400
Message-ID: <18A668FB81B24FB6AFC3AD0D4473E401@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following main electrical system (normal power and lighting) shutdown request for Bldg. NW12 - All, on Monday, July 2, 2012, 10:00am - 10:30am, is for your information and response. Any questions, please contact Rich Lucas, x4-6801.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: July 2, 2012
Day: Monday
Time: 10:00am - 10:30am
Building(s): NW12
Room(s): All
System: Main Electrical System (Normal Power and Lighting)
Duration: 1/2 hour
Reason:
Shutdown of building NW12 All Normal Power and Lighting is required in order to replace two faulty circuit breakers. This is a follow up to our PM and testing done recently. The replacement circuit breakers are here and they will only take 5 to 10 minutes each to swap them out. Because of the complexity of the electrical system we must notify all that they could and probably will lose power for 10 minutes sometime during the half hour designated.
Effect:
Loss of access controls, emergency generator, building power, elevators, computers, telephones, lighting (including corridors/stairs), chilled water, condenser water, hot domestic water, heating hot water, supply ventilation/cooling/heating air, laboratory/general/toilet exhaust, compressed control/lab air, lab vacuum, condensate return, and smoke detectors for the duration of the shutdown.