[159585] in Hotline Meeting
Bldg. 66 - All, Heating Hot Water Shutdown Request
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu Jun 21 13:47:27 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <koskae@MIT.EDU>
Date: Thu, 21 Jun 2012 13:47:24 -0400
Message-ID: <767D643292874A509DD6E71F75E8A760@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following heating hot water shutdown request for Bldg. 66 - All, on Monday, June 25, 2012, 6:00am - 10:00am, is for your information and response. Any questions, please contact Evan Koska, x4-6173.
Please let us know whether this does or does not have your approval.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: June 25, 2012
Day: Monday
Time: 6:00am - 10:00am
Building(s): 66
Room(s): All
System: Heating Hot Water
Duration: 4 hours
Reason:
We request a Building 66-All Heating Hot Water Shutdown from 6:00am until 10:00am on Monday June 25th for Elaine Construction (Nick Murray 617-799-7913) to demolish a heating terminal fan coil unit. MIT Project Manager is Evan Koska 617-592-4468.
Effect:
Loss of heating hot water for the duration of the shutdown.