Bldg. 35 - All, Chilled Water Shutdown Request

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu Jun 21 13:20:03 2012

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <mmcorrei@MIT.EDU>
Date: Thu, 21 Jun 2012 13:19:42 -0400
Message-ID: <FC7C961C82784BF8A249620B4813BE95@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following chilled water shutdown request for Bldg. 35 - All, on Wednesday, June 27, 2012, 8:00am - 1:00pm, is for your information and response.  Any questions, please contact Mike Correira, x8-9174.

Please let us know whether this does or does not have your approval.

Thank you,

Jani Findlay
Repair and Maintenance
x3-6381

Type: Normal
Date: June 27, 2012
Day: Wednesday
Time: 8:00am - 1:00pm
Building(s): 35
Room(s): All
System: Chilled Water
Duration: 5 hours
Reason: 
continuation of Neslab tie-in in the basement - we apologize but after further investigation we need to include the entire building in order to complete this tie-in.  Thank you.

Effect: 
Loss of chilled water for the duration of the shutdown.