Approved Bldg. 9 - All, Normal and Emergency 208V/120V Building

daemon@ATHENA.MIT.EDU (Janine Findlay)
Fri Jun 15 13:50:55 2012

From: Janine Findlay <jfindlay@plant.mit.edu>
To: Ops RM Shutdown <rm-shutdown@mit.edu>,
        "cp-command@mit.edu"
	<cp-command@mit.edu>,
        "safety@mit.edu" <safety@mit.edu>,
        Operators
	<Operators@plant.mit.edu>,
        DOF Customer Service Center <dof-csc@mit.edu>,
        "Ops Custodial Admin & Support Staff" <cust-staff@mit.edu>,
        "shutdowns@mit.edu" <shutdowns@mit.edu>,
        "whomeyer@mit.edu"
	<whomeyer@mit.edu>,
        "Ops RM Electrical Controls Team" <rm-elecctl@mit.edu>,
        "rlucas@mit.edu" <rlucas@mit.edu>, "dcrovo@mit.edu" <dcrovo@mit.edu>,
        "cdh@mit.edu" <cdh@mit.edu>, "craze@mit.edu" <craze@mit.edu>,
        Jim Harrington
	<lordjim@mit.edu>, "laugh@mit.edu" <laugh@mit.edu>,
        OPS RM Campus Services
 Main <rm-mcs@mit.edu>,
        Ops Custodial Admin & Support Staff
	<cust-staff@mit.edu>,
        "jrmac@mit.edu" <jrmac@mit.edu>,
        "segaloff@MIT.EDU"
	<segaloff@mit.edu>,
        "gillooly@MIT.EDU" <gillooly@mit.edu>, "annm@mit.edu"
	<annm@mit.edu>,
        "dgeltner@mit.edu" <dgeltner@mit.edu>,
        "lthoma@MIT.EDU"
	<lthoma@mit.edu>,
        "mvieira@mit.edu" <mvieira@mit.edu>,
        "barnard@mit.edu"
	<barnard@mit.edu>,
        "monaglek@MIT.EDU" <monaglek@mit.edu>,
        "kyegian@MIT.EDU"
	<kyegian@mit.edu>
CC: "jcombs@mit.edu" <jcombs@mit.edu>
Date: Fri, 15 Jun 2012 13:50:51 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE8089F36@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit

The following approved normal and emergency 208v/120v building power shutdown for Bldg. 9 - All, on Monday, June 18, 2012, at 11:00pm through 6:00am on Tuesday, June 19, 2012, is for your information.  Any questions, please contact Billy Homeyer, x8-0432.

Thank you,

Jani Findlay
Repair and Maintenance
x3-6381

Type: Normal
Date: June 18, 2012
Day: Monday
Time: 11:00pm (6/18) - 6:00am (6/19)
Building(s): 9
Room(s): All
System: Normal and Emergency 208V/120V Building Power 
Duration: 7 hours
Reason: 
We request a bldg 9-all normal and emergency 120V/208V power shutdown from 11 PM on Monday evening, June 18th to 6 AM on Tuesday morning, June 19th, 2012 for Reilly Electric to install fire alarm related power monitoring relays within the main 208V switchgear, remove an existing ATS, install a new standby power panel and transfer all non life-safety loads from the existing emergency power panel (becomes life-safety)  to the new stand-by panel and all as part of the bldg 9-fire alarm upgrades project by Elaine Construction (Mike Grandmaison 617-756-1077). Jennifer Combs 3-7671 is the MIT project manager.

Effect: 
Loss of emergency power, building power, elevators, computers, telephones, lighting, compressed control air, condensate return, and sanitary and storm drain drainage for the duration of the shutdown.