[159424] in Hotline Meeting
Approved Bldg. 31 - All, Fire Alarm Shutdown and (possible) *Brief
daemon@ATHENA.MIT.EDU (Janine Findlay)
Thu Jun 14 14:26:03 2012
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "shutdowns@mit.edu" <shutdowns@mit.edu>,
Billy Homeyer
<whomeyer@plant.mit.edu>,
Ops RM Fire Protection Team
<rm-fire-prot-team@mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
DOF Customer Service Center
<dof-csc@mit.edu>,
Ops Custodial Admin & Support Staff <cust-staff@mit.edu>,
"jmletend@mit.edu" <jmletend@mit.edu>,
"oconaill@mit.edu" <oconaill@mit.edu>, "DICKP@MIT.EDU" <DICKP@mit.edu>,
"alz@MIT.EDU" <alz@mit.edu>,
"OPS RM Campus
Services Main" <rm-mcs@mit.edu>,
"herrickd@MIT.EDU" <herrickd@mit.edu>, "thane@mit.edu" <thane@mit.edu>,
"gillooly@MIT.EDU" <gillooly@mit.edu>,
"barnard@mit.edu" <barnard@mit.edu>,
"monaglek@MIT.EDU" <monaglek@mit.edu>
CC: "sinanig@mit.edu" <sinanig@mit.edu>
Date: Thu, 14 Jun 2012 14:26:00 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE8089B4B@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved fire alarm shutdown on Friday, June 15, 2012, 6:00am - 10:00am, and Monday, June 18, 2012, 12:30pm - 4:30pm, with possible *brief live audible testing on Monday, June 18, 2012, between 12:30pm - 4:30pm, for Bldg. 31 - All, is for your information. Any questions, please contact Billy Homeyer, x8-0432.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: June 15, 2012
Day: Friday
Time: 6:00am - 10:00am (6/15); 12:30pm - 4:30pm (6/18)
Building(s): 31
Room(s): All
System: Fire Alarm and *Brief Live Audible Testing
Duration: 4 hours/4 hours
Reason:
We request bldg 31 fire alarm shutdowns on Friday and Monday, June 15th and 18th, 2012 as follows; from 6 AM to 10 AM on Mon 6/15 for Honeywell/Schneider to replace one of the gas sensors in the Vulcane system and from 12:30 PM (or immediately following the bldg 13-3064 O2 depletion system testing*) to 4:30 PM on Monday 6/18 to conduct silent and *brief live audible 3rd party testing of the bldg 31 fire alarm system* in order to test the gas sensing system for the Ghoniem Lab project by Wise Construction (Chris Luongo 781-389-5749). Gerhard Sinani 4-1705 is the MIT project manager.
Please note the live testing may not be necessary but we've included a brief live test just in case.
Effect:
Loss of fire alarms for the duration of the shutdown and possible *brief live audible testing on Monday.