Bldg. W51C - All, Fire Alarm Shutdown Notificaction and *Intermittent Live Audible Testing Request

daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Mon Jun 11 13:41:28 2012

From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <sinanig@MIT.EDU>
Date: Mon, 11 Jun 2012 13:41:25 -0400
Message-ID: <338FECA1971343268F0F21D6CAB1D6DA@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
	charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message

The following fire alarm shutdown notification on Tuesday, June 12, 2012 through Thursday, June 14, 2012, 6:00am - 4:30pm each day, with the *live audible testing from 9:30am - 4:30pm each day, is for your information and response.  Any questions, please contact Billy Homeyer, x8-0432.

Please let us know whether this does or does not have your approval.

Thank you,

Jani Findlay
Repair and Maintenance
x3-6381 

Type: Normal
Date: June 12, 2012
Day: Tuesday
Time: 6:00am - 4:30pm
Building(s): W51C
Room(s): All
System: Fire Alarm and *Intermittent Live Audible Testing
Duration: 10.5 hours/day
Reason: 
We request bldg W51C fire alarm shutdowns from 6 AM to 4:30 PM on Tuesday, Wednesday and Thursday, June 12th, 13th and 14th, 2012 for C&W Electric and Fire Command Systems to work and clear the 3rd party test punch list and to conduct *intermittent live audible 1st and 3rd party testing of the W51C fire alarm system between 9:30 AM and 4:30 PM on all three days* and as part of the W51C building renovation project by O'Connor Constructors (Keith Prior 617-733-8673). Thursday's shutdown is currently tentative. Gerhard Sinani 4-1705 is the MIT project manager.

Effect: 
Loss of fire alarms for the duration of the shutdown and *intermittent live audible testing each day.