[159364] in Hotline Meeting
Approved Bldg. 5 - Basement Labs/Offices, 1st and 2nd Floor
daemon@ATHENA.MIT.EDU (Janine Findlay)
Fri Jun 8 09:38:40 2012
From: Janine Findlay <jfindlay@plant.mit.edu>
To: "shutdowns@mit.edu" <shutdowns@mit.edu>,
Billy Homeyer
<whomeyer@plant.mit.edu>,
Jim Harrington <lordjim@mit.edu>, "laugh@mit.edu"
<laugh@mit.edu>,
"skendall@mit.edu" <skendall@mit.edu>,
"OPS RM Campus
Services Main" <rm-mcs@mit.edu>,
"icuevas@mit.edu" <icuevas@mit.edu>,
"danielle@mit.edu" <danielle@mit.edu>,
"ktanaka@mit.edu" <ktanaka@mit.edu>,
"sbghosh@MIT.EDU" <sbghosh@mit.edu>, "fenner@mit.edu" <fenner@mit.edu>,
"phaley@mit.edu" <phaley@mit.edu>, "khendrk@mit.edu" <khendrk@mit.edu>,
"herrickd@MIT.EDU" <herrickd@mit.edu>,
"pierrel@mit.edu" <pierrel@mit.edu>,
"wgleslie@MIT.EDU" <wgleslie@mit.edu>,
"mistetri@MIT.EDU" <mistetri@mit.edu>, "kurt@mit.edu" <kurt@mit.edu>,
"mleen@mit.edu" <mleen@mit.edu>, "dstidsen@mit.edu" <dstidsen@mit.edu>,
"gillooly@MIT.EDU" <gillooly@mit.edu>, "hover@mit.edu" <hover@mit.edu>,
"annm@mit.edu" <annm@mit.edu>, "wayneb@mit.edu" <wayneb@mit.edu>,
MIT Schedules Office <schedules@mit.edu>,
"barnard@mit.edu" <barnard@mit.edu>,
"jmcollin@mit.edu" <jmcollin@mit.edu>,
"nkaempf@MIT.EDU" <nkaempf@mit.edu>,
"monaglek@MIT.EDU" <monaglek@mit.edu>, "book@mit.edu" <book@mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
DOF Customer Service Center
<dof-csc@mit.edu>,
Ops Custodial Admin & Support Staff <cust-staff@mit.edu>
CC: "sinanig@mit.edu" <sinanig@mit.edu>
Date: Fri, 8 Jun 2012 09:38:36 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE2B648C2@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved air handler 1, exhaust fan 1 (PM #717434) shutdown for Bldg. 5 - Basement Labs/Offices, 1st and 2nd Floor Classrooms, on Saturday, June 9, 2012, at 6:00am through 6:00am on Monday, June 11, 2012, is for your information. Any questions, please contact Billy Homeyer, x8-0432.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: June 9, 2012
Day: Saturday
Time: 6:00am (6/9) through 6:00am (6/11)
Building(s): 5
Room(s): Basement Labs/Offices, 1st and 2nd Floor Classrooms
System: Air Handler 1, Exhaust Fan 1 (PM #717434)
Duration: 48 hours
Reason:
We request bldg 5-AH1/EF1 shutdowns from 6 AM on Saturday, June 9th to 6 AM on Monday, June 11th, 2012 for Ducts Inc (Darren King 617-908-7370)/AHC Mechanical (Guy Fossiano 781-844-7815) to install and seal new supply air and general/fume hood exhaust ductwork in 5-034, 026, 022 as part of a Mech E project, that properly balances air flows in these labs, by Renovations Inc. (Jim Abbisso 617-594-7650). Gerhard Sinani 617-233-1413/4-1705 is the MIT project manager.
*note a minimum of 24 hours is required to allow the duct sealant product to set and cure properly. AH1 also serves 1st and 2nd floor classrooms.
Effect:
Loss of supply ventilation and heating air for the duration of the shutdown.