[159353] in Hotline Meeting
Emergency - Bldg. E19 - 6th and 7th Floors, North side of the building - Chilled Water (comfort cooling) Shutdown Notification
daemon@ATHENA.MIT.EDU (shutdown-response@MIT.EDU)
Thu Jun 7 14:32:02 2012
From: shutdown-response@MIT.EDU
To: <undisclosed_recipients@MIT.EDU>
Cc: <erita@MIT.EDU>, <plyons@MIT.EDU>, <mmcorrei@MIT.EDU>
Date: Thu, 7 Jun 2012 14:31:53 -0400
Message-ID: <58A7BAD40C814A439BA496CD7ED04053@facilities.ms.mit.edu>
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Content-Transfer-Encoding: 7bit
Content-Class: urn:content-classes:message
The following emergency chilled water (comfort cooling) shutdown notification for Bldg. E19 - 6th and 7th Floors, North side of the building, on Thursday, June 7, 2012, 2:30pm - until repairs are complete, is for your information. Any questions, please contact Mike Godding, x3-4948 and ask to have him paged.
We apologize for any inconvenience this may cause you.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Emergency
Date: June 7, 2012
Day: Thursday
Time: 2:30pm - until repairs are complete
Building(s): E19
Room(s): 6th and 7th Floors, North side of the building
System: Chilled Water (comfort cooling)
Duration: until repairs are complete
Reason:
repairs needed for chilled water leak
Effect:
Loss of chilled water (comfort cooling) for the duration of the shutdown.