[159312] in Hotline Meeting
Approved Bldg. 13 - All, Fire Alarm Shutdown and *Brief Live
daemon@ATHENA.MIT.EDU (Janine Findlay)
Tue Jun 5 13:40:20 2012
From: Janine Findlay <jfindlay@plant.mit.edu>
To: Ops RM Fire Protection Team <rm-fire-prot-team@mit.edu>,
"shutdowns@mit.edu" <shutdowns@mit.edu>,
Billy Homeyer
<whomeyer@plant.mit.edu>,
Ops RM Shutdown <rm-shutdown@mit.edu>,
"cp-command@mit.edu" <cp-command@mit.edu>,
"safety@mit.edu" <safety@mit.edu>, Operators <Operators@plant.mit.edu>,
DOF Customer Service Center
<dof-csc@mit.edu>,
Ops Custodial Admin & Support Staff <cust-staff@mit.edu>,
"Leskolo@mit.edu" <Leskolo@mit.edu>,
OPS RM Campus Services Main
<rm-mcs@mit.edu>,
Ops Custodial Admin & Support Staff <cust-staff@mit.edu>,
"jbartels@MIT.EDU" <jbartels@mit.edu>,
"mbulsara@mit.edu" <mbulsara@mit.edu>,
"sdalton@MIT.EDU" <sdalton@mit.edu>,
"jeileef@mit.edu" <jeileef@mit.edu>, "elk@MIT.EDU" <elk@mit.edu>,
"eafitz@MIT.EDU" <eafitz@mit.edu>,
"gillooly@MIT.EDU" <gillooly@mit.edu>,
"wayneb@mit.edu" <wayneb@mit.edu>,
"MIT Schedules Office" <schedules@mit.edu>,
"jingkong@mit.edu"
<jingkong@mit.edu>,
"barnard@mit.edu" <barnard@mit.edu>,
"monaglek@MIT.EDU"
<monaglek@mit.edu>
CC: "biss@mit.edu" <biss@mit.edu>
Date: Tue, 5 Jun 2012 13:40:16 -0400
Message-ID: <4EEA516695C10541B7CB963FF54A56AF0CE2AA01E8@dof-exchmbx01.facilities.ms.mit.edu>
Content-Language: en-US
Content-Type: text/plain; charset="us-ascii"
MIME-Version: 1.0
Content-Transfer-Encoding: 8bit
The following approved fire alarm shutdown and *brief live audible testing for Bldg. 13 - All, on Wednesday, June 6, 2012, 8:00am - 12:00pm, is for your information. Any questions, please contact Billy Homeyer, x8-0432.
Thank you,
Jani Findlay
Repair and Maintenance
x3-6381
Type: Normal
Date: June 6, 2012
Day: Wednesday
Time: 8:00am - 12:00pm
Building(s): 13
Room(s): All
System: Fire Alarm and *Brief Live Audible Testing
Duration: 4 hours max
Reason:
We request bldg 13-all fire alarm shutdown from 8 AM to 12 noon on Wednesday, June 6th, 2012 for Bennett Electric (Jim Vella 781-775-6613) and Simplex (Rich Perron 781-603-7799) to tie-in and program two strobe circuit sync modules and to conduct some brief *live audible 3rd party testing of the bldg 13 fire alarm system*, to be witnessed by JMBCo (Wayne Maginnis 617-212-2059), in order to inspect and test new devices installed for the NSF funded 13-3064 lab renovation project by Barr and Barr Builders (John Bidgood 508-686-0870 or 8-0877). Biss Teelucksingh 2-5972 is the MIT project manager.
Effect:
Loss of fire alarms and *brief live audible testing for the duration of the shutdown.